STATUS

                                                                                          Project 2(03)

                                   District 8

       Claim # 08-030002-01

 


Action                                                                                                             Date Complete

 

                        X         Notice of Intent to File a Claim received.                                                       4/25/05           

                                                           

X         Letter to Contractor requesting Claim Documentation.                                       5/12/05                       

 

X         Claim Documentation received from Contractor (5 copies to CO).                    6/10/05           

 

X         E-mail to District requesting Claim Documentation.                                            6/13/05           

 

X         Claim Documentation received from District (5 copies to CO).                          7/19/05

 

X         Copy of District’s Claim Documentation sent to Contractor.                              7/25/05                       

 

X         Supplemental Claim Documentation received from Contractor.                          8/22/05           

 

X         Hearing scheduled.                                                                                           9/6/05                                     

                                                Date:                9/23/05           

Time:                10:30 am

Location:          Central Office room 1C           

 

X         Hearing date, time, and location confirmed with all parties.                                 9/7/05             

 

X         Claim Documentation distributed to Panel.                                                         9/19/05                       

 

X         Names & phone numbers of those who may present information at the hearing.  9/19/05

 

X         A/V needs for hearing identified.                                                                       9/19/05

 

X         Hearing conducted.                                                                                           9/23/05                                               

X         Decision issued.                                                                                                12/8/05

                                               

0        Contractor either accepts or rejects decision in writing.

 

COMMENTS: